Re: Default Notices
Utter rubbish.
22nd Feb 2007 was a Thursday. If the DN was sent by 2nd class, then the presumed date of service would be 28 February.
Even in (bloody) Yorkshire that only gave two days notice, as 3rd March 2007 was a Saturday and hence probably did not count.
Even if the DN had been sent by Special Delivery or by a fast native bearer with the DN in a cleft stick, it still would not allow 14 days for the default to be remedied.
Originally posted by jon1965
View Post
22nd Feb 2007 was a Thursday. If the DN was sent by 2nd class, then the presumed date of service would be 28 February.
Even in (bloody) Yorkshire that only gave two days notice, as 3rd March 2007 was a Saturday and hence probably did not count.
Even if the DN had been sent by Special Delivery or by a fast native bearer with the DN in a cleft stick, it still would not allow 14 days for the default to be remedied.
Comment